The piling is finished. I missed the pile test, where a selected pile is loaded with large numbers of eight-tonne concrete cubes and the amount of settlement is measured. The next stage is to expose the steel reinforcement to provide something for the concrete ground slab to attach itself to. Normal procedure is to break the concrete at the tops of the piles and thread foundation slab steel into the ground slab steel before pouring the foundation concrete.
The contractor has installed steel I-columns around the perimeter of the building footprint. These act as underground fence posts to hold back adjacent earth while the soil around the piles is excavated. Exactly the same technique was being used in Washington DC, as photographed by nzm.
Not many piles visible. Most are below ground
It is a little unfortunate that the steel columns were installed using a crane with a vibrator attachment; the columns are vibrated so that they glide into the ground, and will presumably be removed using the same technique. Everyone living or working nearby spent a couple of weeks having their dental fillings loosened by the all-pervasive vibration. Still, it's less noisy than a steam hammer donking away all day.
A crane
Now that dewatering has been installed, an excavator can trundle around the site without sinking into a noisome muddy pool. In fact, provided the pump keeps on running the ground will likely remain dry. Groundwater slurps up the little green pipes by suction and is ultimately discharged into a nearby storm sewer.
The consequences of inadequate dewatering
As the excavation started, it quickly became apparent that of all those piles that were installed, initially only two were visible, poking out of the bottom of the excavation. There were several suspicious-looking bent bits of reinforcing steel. I suspect that the tops of some of the piles were inadvertently demolished during the excavation process. Further excavation to around three metres below original ground level finally revealed several other piles. So they didn't all sink without trace into the quagmire. We are now regaled by jackhammers as the concrete is broken out to expose the steel bars.
I have finally managed to upload some pictures, courtesy of Picasa. That's on 22nd July, a week after uploading the text.
9 comments:
Thanks for the explanation - this is what we're currently also enduring with the groundwork for the 2 twisted towers at the Marina entrance - and they haven't really started to excavate in earnest yet!
I had the same problem with Blogger while in NY - photos wouldn't load, it just freezes.
Contacted Blogger who came back to me asking standard questions as well as asking for some sample pic files. After I did all this, the upload started working again.
The Blogger people say that they know about the photo upload problems, but are having difficulties reproducing it. It must be exactly like that annoying squeak or misfire in the car that refuses to manifest when in line of sight of a competent mechanic.
I tried to help them as much as I could - gave them all the answers for their questions, plus image files that I had previously managed to upload, as well as some new ones that weren't being accepted.
I even suggested that it may be a regional thing, since I couldn't upload in New York, (and other NY bloggers were reporting the same issue), but 6 hours later in Washington, I could.
But if it's also happening for you in Dubai, it appears to be a bigger issue.
Blogger upload is weird. I tried it once or twice without success and went back to my old method of FTPing images to one of my own servers. But MamaDuck doesn't have a problem with it, and she's using the same computer!
I do a pile test every morning, usually around 7am.
Things are working normally at the moment, but if the test ever fails you'll be the first to know.
I bet your test doesn't involve cubes that weigh around eight tonnes each. Although it might feel like it.
"The Ooh-Aah bird is so named because it lays square eggs" - Richard Briers in The Good Life
If i've been for a ruby it sure does!
"Dewatering" and "Dubai" seem mutually exclusive. However, if you have some spare water, Thames Water will be happy to receive it. Apparently that which does not leak away is abstracted with only a nominal charge due to inept contract writing. 31 deg in sunny Southsea at the moment:-)
Thirty-one? Pah! It's hotter than that here by moonlight!
Post a Comment